Pennant Walters

Pennant Walters

Pant y Wal

Our Pant y Wal project is located near Blackmill in Bridgend County Borough Council. The Pant y Wal site was first identified in 2004 and land assembled in 2005. Following the completion of EIA studies our original application for a 14 x 3MW site was made in March 2006.  RWE made an application on the neighbouring Fforch Nest site for 13 x 3MW turbines in August 2006 (spanning both Bridgend and Rhondda Cynon Taff boundaries).  In 2008 Bridgend CBC and CCW requested that PWL and RWE co-operate to enable one access route rather than the two separate ones we had to that date brought forward.  We subsequently submitted with RWE a joint access track application in late 2008. 

In 2009 our Bridgend application (then reduced to 10 x 2.5MW turbines) was approved along with the joint access track.  RWE’s application for the 4 (of its then 11 x 2.5MW) turbines in Bridgend CBC was approved at the same planning meeting.  In October 2011 PWL successfully completed the financing of the Pant y Wal project and construction started late in that month.  The RWE Fforch Nest project is being constructed in parallel with Pant y Wal.

Nordex 2.5MW turbines

Construction
 
The major project parties are:
 
Turbine Supply Contract – Nordex
Civil Engineering Contract – Walters UK
Electrical Engineering Contract – Powersystems Ltd
Grid Connection – Western Power Distribution
Walters UK has also assumed the role of principal contractor.
 
The installed capacity of the Pant y Wal site alone will be 25MW.  The final capacity of the Fforch Nest scheme will be 27MW.
 
During operation:
Power Sales Contract – Statkraft
Operations and Maintenance Contract – Nordex
 
Equity Investors – Pennant Walters Ltd and InfraRed Capital Partners Limited (formerly HSBC Specialist Investments Limited)
Debt Financing was provided Lloyds Bank.

Construction is due to complete in April 2013.